Yellow alert lifted in Luzon–NGCP

Credit to Author: The Manila Times| Date: Thu, 16 May 2019 10:03:03 +0000

THE National Grid Corp. of the Philippines (NGCP) has lifted the yellow alert in the Luzon grid due to a lower power demand.

In its advisory, the grid operator said the alert was lifted at 4:37 p.m.

The Department of Energy (DoE) said the 345-megawatt (MW) Unit 1 of GNPower Mariveles Coal Plant Ltd. Co. remained offline and was expected to resume operations on Saturday.

Also, the following power plants are running at limited capacity:

*Calaca Unit 2 of SEM-Calaca Power Corp.
*Pagbilao Unit 3 of Pagbilao Energy Corp.
*Limay Unit 2 of SMC Consolidated Power Corp.
*Angat Hydroelectric Power Plant Main Units 1-4 of Angat Hydropower Corp.
*Pantabangan Hydroelectric Power Plant Units 1-2 of First Gen Hydro Power Corp.
*Magat Hydroelectric Power Plant Units 1-4 and Ambuklao Hydroelectric Power Plant Units 1-3 of SN Aboitiz Power Inc.

The NGCP declares a yellow alert when reserves are less than the capacity of the biggest plant in the grid which is 647 MW for Luzon. JORDEENE B. LAGARE

 

The post Yellow alert lifted in Luzon–NGCP appeared first on The Manila Times Online.