DPWH eyes completion of viral unfinished Bukidnon bridge

MANILA — The Department of Public Works and Highways (DPWH) said Friday it was committed to completing a bridge in Impasug-ong, Bukidnon that was left incomplete due to a lack of funding in the last two years.
The DPWH issued the statement after photos and videos of the bridge went viral on social media.
The bridge appears nearly complete, with a road extending from one side, except for a short unfinished section connecting it to the opposite bank.
The DPWH said the bridge was part of the 169-kilometer Sayre Highway Parallel Road II project, funded by the Japan International Cooperation Agency (JICA), which aims to improve connectivity between Northern Mindanao, which includes Bukidnon, and the Soccsksargen region.
“However, construction was paused because the project received no funding from 2024 to 2026,” the DPWH said.
But the DPWH has allocated funding for the project in the proposed 2027 budget.
“President Marcos has directed Public Works Secretary Banoy Lopez to review the project and find ways to resume construction, as it will improve travel and transport between Misamis Oriental, Bukidnon, and Cotabato,” the DPWH said.
“The DPWH remains committed to completing vital infrastructure that improves the daily lives of Filipinos,” it added.