Senators grill DPWH over multipurpose building funds, stalled expressway bribery claim
The Department of Public Works and Highways (DPWH) building is seen in this photo taken on August 25, 2025. Jonathan Cellona, ABS-CBN News/FileMANILA — Senators on Saturday questioned the Department of Public Works and Highways (DPWH) over the distribution of infrastructure funds, particularly multipurpose buildings and evacuation centers, as well as the status of a stalled expressway project, during their deliberations on the agency’s proposed 2027 budget.
Sen. Panfilo “Ping” Lacson raised concerns over the distribution of multipurpose building (MPB) projects, saying government data showed that most of these were allocated to wealthier local government units (LGUs), while poorer municipalities received significantly fewer projects.
According to figures presented by Lacson, 53,865 out of the 79,816 multipurpose buildings constructed from 2012 to 2026, or 67.5%, were allocated to first-class LGUs.
In contrast, fifth-class municipalities received only 976 projects, equivalent to 1.2% of the total.
“Mukhang mali yung direction,” Lacson said.
He also noted that the government had spent around P760 billion on the construction of 79,816 multipurpose buildings during the period.
Sen. JV Ejercito, who sponsored the DPWH budget, said the Senate finance committee had asked the department to provide more specific descriptions of multipurpose building projects, such as whether these would be barangay halls, daycare centers, covered courts, or evacuation centers.
For 2027, Ejercito said around P40 billion, or 6% of the DPWH’s proposed P643-billion budget, was allocated for multipurpose buildings.
He added that the department would look into prioritizing fourth- and fifth-class municipalities.
Lacson also questioned the proposed allocation for multipurpose buildings in higher-income cities and municipalities, suggesting that some funds could instead be redirected to other infrastructure priorities.
“Baka pwedeng kaltasin na lang natin yung naka-allocate sa mga 1st class, 2nd class na napakaraming multipurpose buildings para ma-realign natin sa ibang priorities,” he said.
He further questioned possible duplication in funding between the Local Government Support Fund-Financial Assistance to Local Government Units (LGSF-FALGU) and the DPWH’s regular infrastructure program.
Lacson said 57 projects worth P618 million funded under LGSF from 2022 to 2026 were also included in the DPWH’s regular programs in the same year, bringing the combined funding to around P1.08 billion.
“Nangyayari po iyan. Minsan po kasi, kapag kulang po ang pondo na nakuha sa isang agency, nanghihingi po sa isang agency para makumpleto o matapos ang kailangan na pondo para macomplete ang construction,” Ejercito explained.
But Lacson rejected the explanation, pointing out that some of the supposedly duplicated projects were funded in the same year.
On evacuation centers, Lacson questioned the department’s proposed P180 million allocation per region, saying the committee had yet to identify the specific projects funded under previous allocations.
Ejercito said P90.674 billion had been allocated from 2016 to 2026 for the construction of 503 evacuation centers nationwide.
As of October 25, 2026, 463 were completed, 29 were under construction, and 11 were in the pre-construction phase, according to the DPWH official.
Ejercito also clarified that earlier evacuation centers were mainly multipurpose buildings that were designated as evacuation centers, while those under the Ligtas Pinoy Centers Act would follow specific designs and standards.
Lacson stressed the need for clearer project descriptions, citing an ongoing structure in Barangay San Agustin, Castillejos, Zambales, which was initially identified only as a multipurpose building but turned out to be a public market.
“We’re not against the construction pero for transparency purpose, dapat talaga may description. Kung palengke, sabihing palengke. Kung sports complex, sabihing sports complex. Huwag lang yung multipurpose building,” Lacson said.
Meanwhile, Sen. Robin Padilla questioned the DPWH’s plans to address persistent flooding in parts of Pampanga and Bulacan, including San Simon, Macabebe, and Calumpit.
Ejercito said the department was following a master plan for the Pampanga River Basin, which includes the construction of five small dams or sabo dams along the Sierra Madre mountain range to slow down water flow.
The plan also includes detention basins in urban areas to temporarily store floodwaters.
Ejercito said feasibility studies for the sabo dams were expected to be completed by the first quarter of 2027, with procurement and civil works targeted to begin by April, provided the project receives sufficient funding.
The exchange turned tense when Padilla brought up the proposed North Luzon East Expressway, a public-private partnership (PPP) project that he said was intended to stretch from Commonwealth Avenue in Quezon City to Bigte in Norzagaray, Bulacan, with succeeding phases reaching Cabanatuan, Nueva Ecija.
Padilla questioned why the project, reportedly proposed as early as 2007, had yet to receive a notice to proceed despite its intended flood mitigation and traffic decongestion benefits.
Ejercito said the project had legal issues.
Padilla then alleged that someone was demanding money to facilitate the project’s approval.
“Madaling araw na, magdiretsahan na po tayo. May humihingi po kasi ng pera dito. Huwag na po tayong maglokohan mainit na ho ulo ko. Umaga na,” Padilla said.
“P100 milyon ang hinihingi dito para lang isapasa. Talaga bang maglolokohan lang tayo dito? PPP ito, walang gastos ang gobyerno dito. Maawa kayo sa mga taong nababaha. Ano bang legal na problema?” he added.
Ejercito said a DPWH official had sought clarification from the PPP Center, which reportedly had yet to approve the project.
At around 1 a.m., Senate Majority Leader Juan Miguel Zubiri moved to refer the matter to the Senate Blue Ribbon Committee for investigation.
“It’s a PPP project. No cost to government. Mukhang pinapahirapan po yung proponent at dahil doon ay hindi talaga matuloy-tuloy yung proyekto siguro pinapahirapan. I move, as chairman of Committee on Rules, that the subjet matter be investigated by the Blue Ribbon Committee,” Zubiri said.
The motion was approved.
Sen. Sherwin Gatchalian said the DPWH would also conduct an internal investigation.
Earlier in the hearing, Lacson also cited the decline in public construction, which he said had fallen for six consecutive quarters.
Based on the figures he presented, government construction declined by 31.5% in the first quarter of 2026, 33.4% in the second quarter, and 15.1% in the third quarter. From January to September, public construction was down 29%.
Ejercito acknowledged delays in project implementation, partly due to issues surrounding flood control projects and stricter safeguards on government spending.
He said the department was working to accelerate disbursements, reporting that it released around P60 billion in October and another P50 billion as of 5 p.m. on Friday.
The Senate finance committee also recommended the deletion of 3,463 projects worth P97.8 billion from the DPWH budget, including 3,132 projects worth P87.2 billion that were flagged for failure to comply with documentary requirements.
However, the committee restored P33.097 billion in funding for foreign-assisted projects, including the Bataan-Cavite Interlink Bridge and the Laguna Lakeshore Road Network Project Phase 1.
Ejercito said the committee’s review was aimed at ensuring that infrastructure spending would support economic growth and accelerate the implementation of priority projects.